At this time, we do not have an update on the completion of the courts. The asphalt plants will open in the spring, and we expect to be first on Beitzel’s schedule to complete the job. After the asphalt is installed, there will be a one-month curing period before the court painting can be done.
We have begun conversations with our pool contractor to clarify the process, review the type of paint that will be used, and determine a potential start date. However, we do not have a confirmed update.
Please be aware there is a possibility that the pool opening could be delayed beyond Memorial Day weekend. That said, if the weather cooperates and obtaining the replacement water is not an issue, the project may still be completed in time.